
For bank valuation / mortgage valuation, it is better to use a stage-wise schedule that separates physical progress, estimated cost incurred, and cost required to complete, rather than assigning an arbitrary percentage merely from visual appearance.
Below is a detailed illustrative schedule for a normal RCC framed residential/commercial building. The percentages should be adjusted for the actual project specifications, floor count, finishes, services and site conditions.
STAGE-WISE CONSTRUCTION COMPLETION & COST-TO-COMPLETE SCHEDULE
Illustrative overall cost distribution
| Sl. | Major Construction Stage | Approx. Share of Total Construction Cost | Cumulative Completion |
|---|---|---|---|
| 1 | Site preparation, survey & setting out | 2% | 2% |
| 2 | Excavation & foundation | 10% | 12% |
| 3 | Plinth & ground preparation | 5% | 17% |
| 4 | RCC frame / structural work | 20% | 37% |
| 5 | Masonry & wall construction | 8% | 45% |
| 6 | Roof, staircase & parapets | 5% | 50% |
| 7 | Electrical/plumbing/HVAC rough-ins | 7% | 57% |
| 8 | Internal & external plastering | 8% | 65% |
| 9 | Flooring & wall tiling | 7% | 72% |
| 10 | Doors, windows & metal work | 5% | 77% |
| 11 | Painting & decorative finishes | 6% | 83% |
| 12 | Fixtures, sanitary & electrical fittings | 5% | 88% |
| 13 | External development | 4% | 92% |
| 14 | Testing, rectification & completion | 3% | 95% |
| 15 | Contingency/remaining minor works | 5% | 100% |
Important: This is an illustrative valuation schedule, not a universally prescribed IBBI percentage table. Actual percentages should be derived from the sanctioned estimate/BOQ, specifications and site inspection.
1. SITE PREPARATION, SURVEY & SETTING OUT
Typical cost allocation: 2%
| Work | Indicative share |
|---|---|
| Survey and site investigation | 0.30% |
| Plot demarcation | 0.15% |
| Site clearing | 0.25% |
| Temporary water/electricity | 0.30% |
| Site establishment | 0.30% |
| Setting out/grid marking | 0.20% |
| Mobilisation/miscellaneous | 0.50% |
| Total | 2.00% |
Physical completion indicators
0–25%: Site cleared
25–50%: Survey completed
50–75%: Building grid established
75–100%: Setting-out completed and excavation ready
Valuer’s observation
Demarcation of the plot does not mean commencement of substantial building construction. It should not be treated as a significant percentage of the building’s structural cost.
2. EXCAVATION & FOUNDATION
Typical cost allocation: 10%
Includes:
- Excavation
- Earthwork
- PCC
- Footings
- Reinforcement
- Formwork
- Foundation concrete
- Pedestals
- Foundation columns
- Anti-termite treatment
- Foundation waterproofing where applicable
- Backfilling
Suggested physical assessment
| Condition observed | Foundation-stage completion |
|---|---|
| Excavation partly completed | 10–25% |
| Excavation complete + PCC | 25–35% |
| Reinforcement/footing work underway | 35–60% |
| Footings completed | 60–75% |
| Foundation columns/pedestals completed | 75–90% |
| Backfilling substantially complete | 90–100% |
3. PLINTH & GROUND PREPARATION
Typical cost allocation: 5%
Includes:
- Plinth beams
- Filling
- Compaction
- DPC
- Ground-floor PCC
- Ground-floor base
- Waterproofing where required
Completion assessment
25%: Plinth beam work started
50%: Plinth beams substantially complete
75%: Filling/compaction substantially complete
100%: DPC and ground-floor base substantially complete
4. RCC FRAME / STRUCTURAL WORK
Typical cost allocation: 20%
This is one of the most important components in stage valuation.
Includes:
- RCC columns
- Beams
- Slabs
- Structural reinforcement
- Formwork
- Concrete
- Staircase structural work
- Structural projections
For a multi-storey building
The valuer should preferably assess floor-wise, rather than saying simply “RCC work 60%.”
Example:
| Structural component | Completion |
|---|---|
| Ground-floor columns | 100% |
| First-floor slab | 100% |
| First-floor columns | 100% |
| Second-floor slab | 80% |
| Roof slab | 0% |
The percentage should then be weighted according to the structural cost attributable to each component.
5. MASONRY / WALL CONSTRUCTION
Typical cost allocation: 8%
Includes:
- External walls
- Internal partition walls
- Brick/AAC/block masonry
- Lintels
- Sill construction
- Chajjas where applicable
- Parapet masonry
Typical assessment
| Work | Approx. completion of this stage |
|---|---|
| Masonry started | 10–20% |
| 25% walls completed | 25% |
| 50% walls completed | 50% |
| 75% walls completed | 75% |
| Masonry substantially complete | 90–100% |
6. ROOF, STAIRCASE & PARAPETS
Typical cost allocation: 5%
Includes:
- Roof slab
- Staircase
- Parapet
- Coping
- Roof slope
- Roof drainage arrangements
A roof slab being completed does not mean that the roof is fully completed. Waterproofing, drainage, protective screed and finishing may still remain.
7. ELECTRICAL, PLUMBING & OTHER SERVICES — ROUGH-IN
Typical cost allocation: 7%
Includes:
- Electrical conduits
- Electrical boxes
- Wiring routes
- Plumbing pipes
- Drainage pipes
- Sanitary pipework
- HVAC sleeves
- Fire-fighting provisions
- Communication/data conduits
Critical valuation point
The valuer should distinguish between:
Concealed/rough-in work
and
Final fixtures and commissioning.
For example, electrical conduits installed in walls should not be treated as equivalent to a completely operational electrical installation.
8. INTERNAL & EXTERNAL PLASTERING
Typical cost allocation: 8%
Includes:
- Internal plaster
- External plaster
- Ceiling plaster
- Surface levelling
- Corners
- Architectural plaster features
- Waterproof exterior treatment where specified
Suggested assessment
25%: Plastering started
50%: Approximately half completed
75%: Major plastering substantially complete
100%: Plastering completed and surfaces ready for finishing
9. FLOORING & WALL TILING
Typical cost allocation: 7%
Includes:
- Floor screed
- Vitrified/ceramic tiles
- Marble/granite/Kota etc.
- Toilet wall tiles
- Kitchen tiles
- Skirting
- Staircase finishes
The valuer should record the type and quality of flooring, because a high-end marble/vitrified specification can materially change the cost.
10. DOORS, WINDOWS & METAL WORK
Typical cost allocation: 5%
Includes:
- Door frames
- Door shutters
- Aluminium/uPVC windows
- Glass
- Ventilators
- Grills
- Railings
- Balcony railing
- Hardware
- Gates
Important
A building with only door/window frames installed should not be considered fully finished under this stage.
11. PAINTING & DECORATIVE FINISHES
Typical cost allocation: 6%
Includes:
- Wall preparation
- Putty
- Primer
- Internal paint
- External paint
- Texture finish
- Polish
- Enamel
- Metal painting
Typical sequence:
Surface preparation → Putty → Primer → First coat → Second/final coat
12. ELECTRICAL & SANITARY FIXTURES
Typical cost allocation: 5%
Includes:
Electrical
- Switches
- Sockets
- Fans
- Light fittings
- DBs
- MCB/RCCB
- Final wiring connections
Sanitary
- WC
- Wash basins
- Faucets
- Showers
- Kitchen sink
- Bathroom accessories
Other
- Water heaters
- Pumps
- Exhaust fans
- Other specified fixtures
13. EXTERNAL DEVELOPMENT
Typical cost allocation: 4%
Includes:
- Boundary wall
- Main gate
- Driveway
- Parking
- Paving
- External drainage
- Landscaping
- Rainwater harvesting
- External water/electrical works
This component can vary substantially depending upon the property.
For a large commercial/industrial property, external development can represent a considerably larger share than in a compact residential building.
14. TESTING, RECTIFICATION & COMPLETION
Typical cost allocation: 3%
Includes:
- Electrical testing
- Plumbing testing
- Waterproofing checks
- Drainage testing
- Fire-fighting testing
- Lift commissioning where applicable
- Snag rectification
- Final cleaning
- Completion-related work
15. COST-TO-COMPLETE CALCULATION
This is particularly important for a bank valuation report.
Suppose:
Estimated total construction cost = ₹1,00,00,000
If the assessed construction progress is 65%, the simplified calculation would be:
| Particular | Amount |
|---|---|
| Total estimated construction cost | ₹1,00,00,000 |
| Cost represented by 65% progress | ₹65,00,000 |
| Estimated balance cost | ₹35,00,000 |
However, a professional valuation should preferably calculate the balance component-wise, rather than merely applying:
Total Cost × (100 − % completion)
because escalation, committed expenditure, incomplete work and specification changes can make the simple calculation misleading.
DETAILED COST-TO-COMPLETE FORMAT
A valuer can use the following format in the valuation report:
| Sl. | Construction Component | Estimated Total Cost | Work Completed | Cost Incurred/Represented | Balance Work | Balance Cost |
|---|---|---|---|---|---|---|
| 1 | Site preparation | ₹2,00,000 | 100% | ₹2,00,000 | 0% | Nil |
| 2 | Foundation | ₹10,00,000 | 100% | ₹10,00,000 | 0% | Nil |
| 3 | Plinth | ₹5,00,000 | 100% | ₹5,00,000 | 0% | Nil |
| 4 | RCC structure | ₹20,00,000 | 90% | ₹18,00,000 | 10% | ₹2,00,000 |
| 5 | Masonry | ₹8,00,000 | 80% | ₹6,40,000 | 20% | ₹1,60,000 |
| 6 | Roof/staircase | ₹5,00,000 | 90% | ₹4,50,000 | 10% | ₹50,000 |
| 7 | Services rough-in | ₹7,00,000 | 60% | ₹4,20,000 | 40% | ₹2,80,000 |
| 8 | Plastering | ₹8,00,000 | 50% | ₹4,00,000 | 50% | ₹4,00,000 |
| 9 | Flooring/tiling | ₹7,00,000 | 20% | ₹1,40,000 | 80% | ₹5,60,000 |
| 10 | Doors/windows | ₹5,00,000 | 30% | ₹1,50,000 | 70% | ₹3,50,000 |
| 11 | Painting | ₹6,00,000 | 10% | ₹60,000 | 90% | ₹5,40,000 |
| 12 | Fixtures | ₹5,00,000 | 5% | ₹25,000 | 95% | ₹4,75,000 |
| 13 | External development | ₹4,00,000 | 25% | ₹1,00,000 | 75% | ₹3,00,000 |
| 14 | Testing/completion | ₹3,00,000 | 0% | Nil | 100% | ₹3,00,000 |
| 15 | Contingency/remaining works | ₹5,00,000 | — | — | — | ₹5,00,000 |
| TOTAL | ₹1,00,00,000 | ₹59,85,000 | ₹40,15,000 |
Thus, in this illustrative example, approximately 59.85% of the cost is represented by completed work and approximately 40.15% remains.
VERY IMPORTANT DISTINCTION FOR VALUERS
A professional valuation report should preferably show three separate concepts:
1. Physical Completion
How much of the building work has actually been completed?
2. Cost Incurred / Cost Represented
What portion of the estimated construction cost is represented by the work completed?
3. Cost to Complete
What expenditure is reasonably required to bring the building to the specified completed condition?
These three figures need not be identical percentages.
For example:
A building may be physically 70% complete but represent only 62% of the total construction cost if the expensive finishing, MEP equipment and fixtures remain.
Conversely:
A project may appear physically only 60% complete but represent 75% of cost if expensive RCC/structural work or specialised equipment has already been completed.
RECOMMENDED FORMAT FOR IBBI/BANK VALUATION REPORT
I recommend inserting the following table in a valuation report:
| Particular | Valuer’s Assessment |
|---|---|
| Total sanctioned/planned built-up area | ____ sq.ft. |
| Total estimated construction cost | ₹________ |
| Estimated cost up to date of valuation | ₹________ |
| Value/cost represented by completed work | ₹________ |
| Physical stage of construction | ____% |
| Cost-based stage of construction | ____% |
| Estimated balance cost to complete | ₹________ |
| Estimated time required for completion | ____ months |
| Quality/specification | Standard / Good / Premium |
| Construction status | Under construction / Near completion |
| Whether construction conforms to sanctioned plan | Yes / No / Partly |
| Major incomplete items | __________ |
| Major deviations observed | __________ |
| Basis of cost estimate | BOQ / CPWD/PWD rates / market rates / contractor estimate / other |
| Date of physical inspection | __________ |
Suggested wording in the valuation report
“Based upon physical inspection of the property and assessment of the various components of construction, the building is observed to be approximately ____% complete in physical terms. On a cost-weighted basis, the completed works represent approximately ____% of the estimated total construction cost. The estimated balance expenditure required to complete the construction to the observed/specified standard is approximately ₹________, subject to escalation in material and labour rates, changes in specifications, statutory requirements and other site-specific conditions.”
This distinction is particularly useful when preparing bank mortgage valuations, stage-wise disbursement assessments, progress reports and valuation of incomplete/under-construction properties.
Disclaimer: यह article general educational information के लिए है। Building laws, Master Plans, zoning regulations, compounding provisions और demolition procedures State/UT तथा local authority के अनुसार अलग हो सकते हैं। किसी specific property पर legal conclusion लेने से पहले current applicable law, municipal records और case-specific professional/legal advice की जांच आवश्यक है।

https://youtu.be/XRCXR4aw6Bo?si=IKuK_L6VnaJnl-43


