CTN PRESS

CTN PRESS

NEWS & BLOGS EXCLUCIVELY FOR INFORMATION TO ENGINEERS & VALUERS COMMUNITY

STAGE-WISE CONSTRUCTION COMPLETION & COST-TO-COMPLETE SCHEDULE FOR BANKS & INCOME TAX VALUATIONS

For bank valuation / mortgage valuation, it is better to use a stage-wise schedule that separates physical progress, estimated cost incurred, and cost required to complete, rather than assigning an arbitrary percentage merely from visual appearance.

Below is a detailed illustrative schedule for a normal RCC framed residential/commercial building. The percentages should be adjusted for the actual project specifications, floor count, finishes, services and site conditions.

STAGE-WISE CONSTRUCTION COMPLETION & COST-TO-COMPLETE SCHEDULE

Illustrative overall cost distribution

Sl. Major Construction Stage Approx. Share of Total Construction Cost Cumulative Completion
1 Site preparation, survey & setting out 2% 2%
2 Excavation & foundation 10% 12%
3 Plinth & ground preparation 5% 17%
4 RCC frame / structural work 20% 37%
5 Masonry & wall construction 8% 45%
6 Roof, staircase & parapets 5% 50%
7 Electrical/plumbing/HVAC rough-ins 7% 57%
8 Internal & external plastering 8% 65%
9 Flooring & wall tiling 7% 72%
10 Doors, windows & metal work 5% 77%
11 Painting & decorative finishes 6% 83%
12 Fixtures, sanitary & electrical fittings 5% 88%
13 External development 4% 92%
14 Testing, rectification & completion 3% 95%
15 Contingency/remaining minor works 5% 100%

Important: This is an illustrative valuation schedule, not a universally prescribed IBBI percentage table. Actual percentages should be derived from the sanctioned estimate/BOQ, specifications and site inspection.


1. SITE PREPARATION, SURVEY & SETTING OUT

Typical cost allocation: 2%

Work Indicative share
Survey and site investigation 0.30%
Plot demarcation 0.15%
Site clearing 0.25%
Temporary water/electricity 0.30%
Site establishment 0.30%
Setting out/grid marking 0.20%
Mobilisation/miscellaneous 0.50%
Total 2.00%

Physical completion indicators

0–25%: Site cleared
25–50%: Survey completed
50–75%: Building grid established
75–100%: Setting-out completed and excavation ready

Valuer’s observation

Demarcation of the plot does not mean commencement of substantial building construction. It should not be treated as a significant percentage of the building’s structural cost.


2. EXCAVATION & FOUNDATION

Typical cost allocation: 10%

Includes:

  • Excavation
  • Earthwork
  • PCC
  • Footings
  • Reinforcement
  • Formwork
  • Foundation concrete
  • Pedestals
  • Foundation columns
  • Anti-termite treatment
  • Foundation waterproofing where applicable
  • Backfilling

Suggested physical assessment

Condition observed Foundation-stage completion
Excavation partly completed 10–25%
Excavation complete + PCC 25–35%
Reinforcement/footing work underway 35–60%
Footings completed 60–75%
Foundation columns/pedestals completed 75–90%
Backfilling substantially complete 90–100%

3. PLINTH & GROUND PREPARATION

Typical cost allocation: 5%

Includes:

  • Plinth beams
  • Filling
  • Compaction
  • DPC
  • Ground-floor PCC
  • Ground-floor base
  • Waterproofing where required

Completion assessment

25%: Plinth beam work started
50%: Plinth beams substantially complete
75%: Filling/compaction substantially complete
100%: DPC and ground-floor base substantially complete


4. RCC FRAME / STRUCTURAL WORK

Typical cost allocation: 20%

This is one of the most important components in stage valuation.

Includes:

  • RCC columns
  • Beams
  • Slabs
  • Structural reinforcement
  • Formwork
  • Concrete
  • Staircase structural work
  • Structural projections

For a multi-storey building

The valuer should preferably assess floor-wise, rather than saying simply “RCC work 60%.”

Example:

Structural component Completion
Ground-floor columns 100%
First-floor slab 100%
First-floor columns 100%
Second-floor slab 80%
Roof slab 0%

The percentage should then be weighted according to the structural cost attributable to each component.


5. MASONRY / WALL CONSTRUCTION

Typical cost allocation: 8%

Includes:

  • External walls
  • Internal partition walls
  • Brick/AAC/block masonry
  • Lintels
  • Sill construction
  • Chajjas where applicable
  • Parapet masonry

Typical assessment

Work Approx. completion of this stage
Masonry started 10–20%
25% walls completed 25%
50% walls completed 50%
75% walls completed 75%
Masonry substantially complete 90–100%

6. ROOF, STAIRCASE & PARAPETS

Typical cost allocation: 5%

Includes:

  • Roof slab
  • Staircase
  • Parapet
  • Coping
  • Roof slope
  • Roof drainage arrangements

A roof slab being completed does not mean that the roof is fully completed. Waterproofing, drainage, protective screed and finishing may still remain.


7. ELECTRICAL, PLUMBING & OTHER SERVICES — ROUGH-IN

Typical cost allocation: 7%

Includes:

  • Electrical conduits
  • Electrical boxes
  • Wiring routes
  • Plumbing pipes
  • Drainage pipes
  • Sanitary pipework
  • HVAC sleeves
  • Fire-fighting provisions
  • Communication/data conduits

Critical valuation point

The valuer should distinguish between:

Concealed/rough-in work
and
Final fixtures and commissioning.

For example, electrical conduits installed in walls should not be treated as equivalent to a completely operational electrical installation.


8. INTERNAL & EXTERNAL PLASTERING

Typical cost allocation: 8%

Includes:

  • Internal plaster
  • External plaster
  • Ceiling plaster
  • Surface levelling
  • Corners
  • Architectural plaster features
  • Waterproof exterior treatment where specified

Suggested assessment

25%: Plastering started
50%: Approximately half completed
75%: Major plastering substantially complete
100%: Plastering completed and surfaces ready for finishing


9. FLOORING & WALL TILING

Typical cost allocation: 7%

Includes:

  • Floor screed
  • Vitrified/ceramic tiles
  • Marble/granite/Kota etc.
  • Toilet wall tiles
  • Kitchen tiles
  • Skirting
  • Staircase finishes

The valuer should record the type and quality of flooring, because a high-end marble/vitrified specification can materially change the cost.


10. DOORS, WINDOWS & METAL WORK

Typical cost allocation: 5%

Includes:

  • Door frames
  • Door shutters
  • Aluminium/uPVC windows
  • Glass
  • Ventilators
  • Grills
  • Railings
  • Balcony railing
  • Hardware
  • Gates

Important

A building with only door/window frames installed should not be considered fully finished under this stage.


11. PAINTING & DECORATIVE FINISHES

Typical cost allocation: 6%

Includes:

  • Wall preparation
  • Putty
  • Primer
  • Internal paint
  • External paint
  • Texture finish
  • Polish
  • Enamel
  • Metal painting

Typical sequence:

Surface preparation → Putty → Primer → First coat → Second/final coat


12. ELECTRICAL & SANITARY FIXTURES

Typical cost allocation: 5%

Includes:

Electrical

  • Switches
  • Sockets
  • Fans
  • Light fittings
  • DBs
  • MCB/RCCB
  • Final wiring connections

Sanitary

  • WC
  • Wash basins
  • Faucets
  • Showers
  • Kitchen sink
  • Bathroom accessories

Other

  • Water heaters
  • Pumps
  • Exhaust fans
  • Other specified fixtures

13. EXTERNAL DEVELOPMENT

Typical cost allocation: 4%

Includes:

  • Boundary wall
  • Main gate
  • Driveway
  • Parking
  • Paving
  • External drainage
  • Landscaping
  • Rainwater harvesting
  • External water/electrical works

This component can vary substantially depending upon the property.

For a large commercial/industrial property, external development can represent a considerably larger share than in a compact residential building.


14. TESTING, RECTIFICATION & COMPLETION

Typical cost allocation: 3%

Includes:

  • Electrical testing
  • Plumbing testing
  • Waterproofing checks
  • Drainage testing
  • Fire-fighting testing
  • Lift commissioning where applicable
  • Snag rectification
  • Final cleaning
  • Completion-related work

15. COST-TO-COMPLETE CALCULATION

This is particularly important for a bank valuation report.

Suppose:

Estimated total construction cost = ₹1,00,00,000

If the assessed construction progress is 65%, the simplified calculation would be:

Particular Amount
Total estimated construction cost ₹1,00,00,000
Cost represented by 65% progress ₹65,00,000
Estimated balance cost ₹35,00,000

However, a professional valuation should preferably calculate the balance component-wise, rather than merely applying:

Total Cost × (100 − % completion)

because escalation, committed expenditure, incomplete work and specification changes can make the simple calculation misleading.


DETAILED COST-TO-COMPLETE FORMAT

A valuer can use the following format in the valuation report:

Sl. Construction Component Estimated Total Cost Work Completed Cost Incurred/Represented Balance Work Balance Cost
1 Site preparation ₹2,00,000 100% ₹2,00,000 0% Nil
2 Foundation ₹10,00,000 100% ₹10,00,000 0% Nil
3 Plinth ₹5,00,000 100% ₹5,00,000 0% Nil
4 RCC structure ₹20,00,000 90% ₹18,00,000 10% ₹2,00,000
5 Masonry ₹8,00,000 80% ₹6,40,000 20% ₹1,60,000
6 Roof/staircase ₹5,00,000 90% ₹4,50,000 10% ₹50,000
7 Services rough-in ₹7,00,000 60% ₹4,20,000 40% ₹2,80,000
8 Plastering ₹8,00,000 50% ₹4,00,000 50% ₹4,00,000
9 Flooring/tiling ₹7,00,000 20% ₹1,40,000 80% ₹5,60,000
10 Doors/windows ₹5,00,000 30% ₹1,50,000 70% ₹3,50,000
11 Painting ₹6,00,000 10% ₹60,000 90% ₹5,40,000
12 Fixtures ₹5,00,000 5% ₹25,000 95% ₹4,75,000
13 External development ₹4,00,000 25% ₹1,00,000 75% ₹3,00,000
14 Testing/completion ₹3,00,000 0% Nil 100% ₹3,00,000
15 Contingency/remaining works ₹5,00,000 — — — ₹5,00,000
TOTAL ₹1,00,00,000 ₹59,85,000 ₹40,15,000

Thus, in this illustrative example, approximately 59.85% of the cost is represented by completed work and approximately 40.15% remains.


VERY IMPORTANT DISTINCTION FOR VALUERS

A professional valuation report should preferably show three separate concepts:

1. Physical Completion

How much of the building work has actually been completed?

2. Cost Incurred / Cost Represented

What portion of the estimated construction cost is represented by the work completed?

3. Cost to Complete

What expenditure is reasonably required to bring the building to the specified completed condition?

These three figures need not be identical percentages.

For example:

A building may be physically 70% complete but represent only 62% of the total construction cost if the expensive finishing, MEP equipment and fixtures remain.

Conversely:

A project may appear physically only 60% complete but represent 75% of cost if expensive RCC/structural work or specialised equipment has already been completed.


RECOMMENDED FORMAT FOR IBBI/BANK VALUATION REPORT

I recommend inserting the following table in a valuation report:

Particular Valuer’s Assessment
Total sanctioned/planned built-up area ____ sq.ft.
Total estimated construction cost ₹________
Estimated cost up to date of valuation ₹________
Value/cost represented by completed work ₹________
Physical stage of construction ____%
Cost-based stage of construction ____%
Estimated balance cost to complete ₹________
Estimated time required for completion ____ months
Quality/specification Standard / Good / Premium
Construction status Under construction / Near completion
Whether construction conforms to sanctioned plan Yes / No / Partly
Major incomplete items __________
Major deviations observed __________
Basis of cost estimate BOQ / CPWD/PWD rates / market rates / contractor estimate / other
Date of physical inspection __________

Suggested wording in the valuation report

“Based upon physical inspection of the property and assessment of the various components of construction, the building is observed to be approximately ____% complete in physical terms. On a cost-weighted basis, the completed works represent approximately ____% of the estimated total construction cost. The estimated balance expenditure required to complete the construction to the observed/specified standard is approximately ₹________, subject to escalation in material and labour rates, changes in specifications, statutory requirements and other site-specific conditions.”

This distinction is particularly useful when preparing bank mortgage valuations, stage-wise disbursement assessments, progress reports and valuation of incomplete/under-construction properties.


Disclaimer: यह article general educational information के लिए है। Building laws, Master Plans, zoning regulations, compounding provisions और demolition procedures State/UT तथा local authority के अनुसार अलग हो सकते हैं। किसी specific property पर legal conclusion लेने से पहले current applicable law, municipal records और case-specific professional/legal advice की जांच आवश्यक है।

 



https://youtu.be/XRCXR4aw6Bo?si=IKuK_L6VnaJnl-43

Leave a Comment

error: Content is protected !!
Scroll to Top